Building act and contract

If the certificate of Non-Completion has been issued on 30th December 2008 and the Extension of TIme was not approved , the Contractor only finished theoir work on 15th January 2009  . How much Liquidated Ascertained Damanges that Contractor has to pay to the client ?

15 days x RM 2,250.00 = RM 33,750.00


C) Based on the Table Q6 what is the total amount of variation works ?
 
  Total variation works  = adjusted sums - contract sum

= RM 5,900 , 000.00 - RM 5,000,00.00
=RM 900 ,000 .00