  1. clearing site of undergroth bushes , scrub  and the like and including grubbing up their roots and removing from site . 
  2. Cutting down trees not exceeding 300mm girth at 1.00 above ground level and grubbing up their roots and filling voids left by removal of roots with material arising from excavation . 
  3. Cutting down trees exceeding 300mm but not exceeding 600mm girth at 1.00m above ground level and grubbing up their roots and filling voids left by removal of roots with material arising from excavation . 
  4. Cutting down trees exceeding 1800mm but not exceeding 2100mm girth at 1.00m above ground level and grubbing up their roots and filling void left by removal of roots with material arising from excavation . 
  5. Removing from site existing tree stumps not exceeding 300mm but not exceeding 600mm girth at 1.oom above ground level or at their tops . I f lower in ehight and grubbing up their roots and filling voids left by removal of roots with material arising from excavation . 
  6. Removing from site existing tree stumps exceeding 300mm but not exceeding 600mm girth at above 1.00m ground level ,or at their top , if lower in height and grubbing up their roots and filling voids left by the removal of roots with material arising from excavation . 
  7. Removing from site existing tree stump exceeding 2100mm but not exceeding 24000mm girth at 1.00m above ground level or at their top if lower in height , and grubbing up their roots and  filling voids left by the removal of roots with material arising from excavation . 
  8. Cutting down yew hedges average 350mm high and grubbing up their roots and filling voids left by removal of roots with material arising from excavation .